Decision Maker: Renewal, Recreation and Housing Policy Development and Scrutiny Committee
Is Key decision?: No
Is subject to call in?: No
Report FSD20009
On 27 November 2019, the Executive received the 2rd quarterly capital monitoring report for 2019/20 and agreed a revised Capital Programme for the four year period 2019/20 to 2022/23.
Members considered changes agreed by the Executive in respect of the Capital Programme for the Renewal, Recreation and Housing Portfolio.
In opening the discussion the Chairman noted a correction to the table in paragraph 3.1 of the report – the 8th line should read “Schemes rephased”. Changed from “schemes rephased from 2019/20 into 2020/21” which was not correct.
In response to a question, the Director of Housing, Planning and Regeneration confirmed that work on the Star Lane traveller site was progressing slowly but it was hoped that there would be a further update by the end of the week.
RESOLVED that the Portfolio Holder be recommended to confirm the changes agreed by the Executive on 27 November 2019.
Report author: James Mullender
Publication date: 25/03/2020
Date of decision: 21/01/2020
Decided at meeting: 21/01/2020 - Renewal, Recreation and Housing Policy Development and Scrutiny Committee
Accompanying Documents: