Description of application - Demolition of existing buildings and redevelopment to form 25 sheltered apartments for the elderly, including communal facilities, access, car parking and landscaping.

 

Oral representations from Ward Member, Councillor Graham Arthur, in support of the application were received at the meeting.  A late objection from the neighbour had been received.  It was reported that the application had been amended by revised plans received on 9 December 2019.

 

It was also reported that on page 108 of the Assistant Director (Planning) report paragraph 4 should be amended to read, “Car Parking- Twenty five car parking spaces (inclusive of 2 disabled spaces) are indicated on the submitted plans; which is satisfactory.”

 

 

Members having considered the report, objections,and representations, RESOLVED that PERMISSION BE GRANTED, SUBJECT TO THE PRIOR COMPLETION OF A LEGAL AGREEMENT TO SECURE:-

  • HEALTHCARE CONTRIBUTION OF £24,098.00
  • CARBON OFFSET CONTRIBUTION OF £47,470.00
  • AFFORDABLE HOUSING PAYMENT-IN-LIEU OF £448,432.00

as recommended and subject to the conditions and informatives set out in the report of the Assistant Director, Planning with amendments to Conditions 4 and  6 and 14,  the removal of Condition 8 and the addition of three further conditions to read:-

 

“AMENDMENT TO CONDITION 4:  The development permitted by this planning permission shall not commence until the detailed design of the measures in the submitted "Drainage Strategy" Report carried out by Arch Associates Consulting with Project No. RRL038 dated July have been submitted to, and approved by, the Local Planning Authority. The scheme shall be carried out in accordance with the approved details and completed before any part of the development is first occupied, and permanently retained thereafter.

REASON: In order to comply with Policy 5.13 of the London Plan and to reduce the impact of flooding both to and from the proposed development and third parties.

 

AMENDMENT TO CONDITION 6:  No development shall commence on site (including demolition) until such time as a Construction and Environmental Management Plan has been submitted to and approved in writing by the local planning authority.  As a minimum the plan shall cover:

 

  (a) Dust mitigation and management measures,

 

  (b) The location and operation of plant and wheel washing facilities,

 

  (c) Measure to reduce demolition and construction noise,

 

  (d) Details of construction traffic movements including cumulative 

     impacts which shall demonstrate the following:-

  (i) Rationalise travel and traffic routes to and from the site as well as

    within the site.

  (ii) Provide full details of the number and time of construction vehicle

    trips to the site with the intention and aim of reducing the impact of

    construction related activity.

  (iii) Measures to deal with safe pedestrian movement.

  (iv) Full contact details of the site and project manager responsible for

    day-to-day management of the works 

  (v) Parking for  operatives during construction period

  (vi) A swept path drawings for any tight manoeuvres on vehicle routes

    to and from the site including proposed access and egress

    arrangements at the site boundary,

 

  (e)  Hours of operation,

 

  (f)  Other site specific Highways and Environmental Protection issues