CRYSTAL PALACE PARK REGENERATION PLAN - PROCEED TO PROCUREMENT FOR CAPITAL WORKS

Decision Maker: Executive

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: No

Decision:

That

1.   Proceeding to procurement, as set out in paragraphs 3.12 to 3.26, for a main contractor to deliver the capital works at a total estimated contract cost of £17.7m be approved.

2.   The budget of the Crystal Palace Park Regeneration Plan already on the Capital Programme by £19.096m be increased. The scheme will be funded through a £5m grant from the National Lottery Heritage Fund and the capital receipts from the sale of the two areas of parkland which are estimated to achieve £19.36m.

 

 

Report author: Tom Bevan

Publication date: 18/04/2024

Date of decision: 18/04/2024

Decided at meeting: 18/04/2024 - Executive