Decision details

PROVISION OF LIBRARY SERVICE - CONTRACT PERFORMANCE REPORT

Decision Maker: Executive, Portfolio Holder for Renewal, Recreation and Housing

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Purpose:

Update on the performance of the Library Service contract over the last six months.

Decision:

1.  The performance of the Library Services contract delivered by the operator Greenwich Leisure Limited (GLL) as detailed within this report be noted;

2.  The detail of contract modifications applied to the Library Services contract to date, summarised in paragraph 3.17 Tables 1 & 2 and detailed in Appendix 2 be noted;

3.  Contract modifications to the Library Services contract relating to the Library Repair programme at an overall estimated value of £1,133k as set out in paragraphs 3.18 to 3.22 be approved noting that there is no additional funding requirement; and,

4.  It be noted that further contract modifications to the Library Services contract are expected, linked to the Library Repair programme, and are asked to approve the scheme of delegation to manage future contract modifications as set out in paragraphs 3.23 to 3.29.

 

Report author: Paula Young

Publication date: 11/07/2024

Date of decision: 10/07/2024

Decided at meeting: 10/07/2024 - Executive