Decision Maker: Portfolio Holder for Renewal, Recreation and Housing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
1) The findings of the Post Completion Reviews carried out in respect of Replacement Chillers at Central Library/Churchill Theatre be endorsed.
2) The removal of the unspent balance of £36k from the capital programme be noted.
As part of the Capital Programme Procedures it is a requirement that schemes should be formally reviewed within one year of completion and the outcome of this review be brought to the Portfolio Holder for consideration and endorsement.
Publication date: 03/11/2017
Date of decision: 03/11/2017
Effective from: 11/11/2017
Accompanying Documents: