Decision details

PENGE AND ANERLEY LIBRARY CAPITAL SCHEME POST COMPLETION REPORT

Decision Maker: Portfolio Holder for Renewal, Recreation and Housing

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Part 1

Decision:

The findings of the Post Completion Review carried out in respect of Penge and Anerley Libraries be endorsed.

Reasons for the decision:

One of the main aims of the Council’s Asset Management Plan is to ensure that all the partners in the asset management planning processes are fully consulted on the process and its outcomes.  Progression of amalgamating the former Anerley/Penge Libraries and providing improved library facilities at 46 Green Lane contributes to the Building a Better Bromley to promote vibrant thriving town centres.

Publication date: 16/11/2018

Date of decision: 16/11/2018

Effective from: 24/11/2018

Accompanying Documents: