Decision Maker: Executive
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
1) The contents of the report be noted;
2) The Operational Estate Strategy as detailed at 3.22 to 3.30 of the report be adopted;
3) Officers progress the various Workstreams identified at 3.34 to 3.43 of the report noting that works packages once scoped and costed will then be reported to the Executive for consideration to proceed and award works packages;
4) The sums identified within the report are incorporated into the Capital Programme;
5) The funding of the £3M resources identified at 3.45 of the report be agreed in principle to enable Officers to progress the various Workstreams and such funding to made available from the Capital Programme.
Report author: Hannah Jackson
Publication date: 01/12/2022
Date of decision: 30/11/2022
Decided at meeting: 30/11/2022 - Executive
Accompanying Documents: