95 ASSET MANAGEMENT PLANNING - POST COMPLETION REVIEW REPORTS PDF 171 KB
Minutes:
Report DCYP12037
The Portfolio Holder introduced a report providing post completion review reports on works carried out at Riverside Beckenham Autistic Centre, Kingswood Pupil Referral Unit and Biggin Hill Primary School. The Capital Programme Procedures require that a post completion review be carried out within 12 months of the completion of schemes that were included within the programme.
The Chairman was disappointed at the costs associated with Riverside such as the roofing and the fencing and asked why this had not been anticipated. He was informed that this was because the school had been marked for closure and had stood empty for some time. There was also a need to open the new school as soon as possible to reduce the costs of pupils going out of borough for ASD provision. Consequently there had been additional costs.
RESOLVED that the Portfolio Holder be recommended to endorse the findings of the Post Completion Reviews carried out in respect of: