35 CAPITAL PROGRAMME MONITORING - 2ND QUARTER 2015/16 PDF 167 KB
Additional documents:
Minutes:
Report FSD16015
On 2 December 2015, the Executive received the second quarterly capital monitoring report for 2015/16 and agreed a revised Capital Programme for the four year period 2015/16 to 2018/19. The report highlighted changes agreed by the Executive in respect of the Capital Programme for the Renewal and Recreation Portfolio and outlined progress achieved as at the end of the first half of 2015/16.
Reasons for the £15k reduction in the Bromley North Village Scheme (Section 3.3), were explained to Members.
RESOLVED that the Portfolio Holder be recommended to confirm the changes agreed by the Executive in December 2015.