Report DRR16/063

 

In compliance with Capital Programme Procedures, a post completion review was undertaken of the improvement works to the former Chartwell Business Centre.

 

The scheme was completed within budget at £11k below the latest approved capital estimate and the balance would be returned to capital receipts. The original contract programme had also been met.

 

A full analysis of the project was appended to Report DRR16/063.

 

Noting that there continued to be occupation by contractors providing services for Environment and Community Services, an enquiry was made on whether all personnel could be moved to the Central Depot. The Environment PDS Chairman understood that street lighting staff had moved but was unsure of the position concerning any personnel that might be remaining.

 

Members commended the scheme completing at £11k below the latest approved capital estimate.

 

RESOLVED that that the Resources Portfolio Holder be recommended to