19 POST COMPLETION REVIEW REPORT – STAND-BY GENERATORS FOR DEPOTS PDF 183 KB
Minutes:
Report ES17061
The Committee considered a post implementation review of the acquisition of stand-by generators for use at depots.
To ensure that the depots were able to function in the event of a total or partial loss of electrical power it was considered necessary to provide back-up power in order to minimise disruption to essential services operating from the depots.
The Chairman noted that the scheme completed within budget and the original contract programme was met.
RESOLVED: That the Portfolio Holder be recommended to:
1. Endorse the findings of the Post Completion Review that has been carried out in respect of Stand-by Generators for Depots.
2. Notes that the unspent balance will be removed from the capital programme.