Issue - meetings

POST COMPLETION REVIEW REPORT – STAND-BY GENERATORS FOR DEPOTS

Meeting: 05/10/2017 - Environment and Community Services Policy Development and Scrutiny Committee (Item 19)

19 POST COMPLETION REVIEW REPORT – STAND-BY GENERATORS FOR DEPOTS pdf icon PDF 183 KB

Minutes:

Report ES17061

 

The Committee considered a post implementation review of the acquisition of stand-by generators for use at depots.

 

To ensure that the depots were able to function in the event of a total or partial loss of electrical power it was considered necessary to provide back-up power in order to minimise disruption to essential services operating from the depots. 

 

The Chairman noted that the scheme completed within budget and the original contract programme was met.

 

RESOLVED: That the Portfolio Holder be recommended to:

 

1. Endorse the findings of the Post Completion Review that has been carried out in respect of Stand-by Generators for Depots.

2. Notes that the unspent balance will be removed from the capital programme.