32 CAPITAL PROGRAMME MONITORING - 1ST QUARTER 2018/19 PDF 82 KB
Additional documents:
Minutes:
Report FSD18072
On 11 July 2018, the Executive received the 1st quarterly capital monitoring report for 2018/19 and agreed a revised Capital Programme for the four year period 2018/19 to 2021/22.
Members considered changes agreed by the Executive in respect of the Capital Programme for the Renewal, Recreation and Housing Portfolio.
Councillor Sharma requested to see a breakdown of the Consultancy Fee Bid for the West Wickham leisure/library development. The Director of Regeneration informed Members that a report would be considered by the Commissioning Board on 24 September which would then allow for the appointment of the multi-disciplinary consultancy team. The PDS Committee would be in a position to scrutinise the project prior to the submission of the planning application before a final decision was taken by Executive Members.
RESOLVED that the Portfolio Holder be recommended to confirm the changes agreed by the Executive on 11 July 2018.