46 PENGE AND ANERLEY LIBRARY CAPITAL SCHEME POST COMPLETION REPORT PDF 135 KB
Minutes:
Report DRR18/054
The Committee considered the post completion report for the Penge and Anerley Library Capital Scheme. As part of the Capital Programme Procedures it was a requirement that schemes should be formally reviewed within one year of completion and the outcome of the review brought to the Portfolio Holder for endorsement.
The Chairman was pleased to note that the Capital Scheme completed below budget and the original contract programme was met.
RESOLVED that the Portfolio Holder be recommended to endorse the findings of the Post Completion Review carried out in respect of Penge and Anerley Libraries.