31 CAPITAL PROGRAMME MONITORING - 1ST QUARTER 2020/21 PDF 660 KB
Additional documents:
Minutes:
Report FSD20066
On 8th July 2020, the Leader received a report summarising the current position on capital expenditure and receipts following the 1st quarter of 2020/21, and agreed a revised Capital Programme for the four year period 2020/21 to 2023/24. The report highlighted changes agreed by the Executive and the Leader in respect of the Capital Programme for the Executive, Resources & Contracts Portfolio. The revised programme for the portfolio was set out in Appendix A to the report and detailed comments on individual schemes were shown in Appendix B, with details of the 2019/20 outturn position are included in Appendix C.
RESOLVED: That the Portfolio Holder be recommended to note the changes agreed by the Leader on 8th July 2020.