217 KELSEY PARK REPLACEMENT BRIDGES PDF 216 KB
To outline progress made on replacement of two
footbridges within Kelsey Park.
Minutes:
ES20208
A discussion took place as to whether or not cycling was permitted in Bromley Parks. It was explained that the current cost estimates that had been received for Kelsey Park replacement bridges was too high and so the Council was exploring the possibility of using different providers to reduce costs; there would be an update provided to the Committee in November.
RESOLVED that:
1) The Committee note the progress made on sourcing replacement structures to the Kelsey Park Bridges.
2) Officers should continue to explore the market for a value for money solution with a further report to follow at the ECS PDS Committee meeting on November 22nd 2022.