Issue - meetings

Procurement of Consultancy Services for the Crystal Palace Park Regeneration Plan

Meeting: 08/02/2023 - Executive (Item 145)

145 PROCUREMENT OF CONSULTANCY SERVICES FOR THE CRYSTAL PALACE PARK REGENERATION PLAN pdf icon PDF 242 KB

Minutes:

Report HPR2023/007

 

The report provided Members with an update on the delivery of the Crystal Palace Park Regeneration Plan, including the recommendation to procure consultancy services for the capital schemes. The report was marked as Urgent as the project would be utilising grant funding which had timescales attached for delivery. Call in would therefore not apply.

The report had been scrutinised by the Renewal, Recreation and Housing PDS Committee at its meeting on 23 January 2023 and the Committee had supported the recommendations.

 

RESOLVED: That

 

1.  The contents of the report be noted, namely information regarding the procurement of the multi-disciplinary consultancy services for the next stages of the Regeneration Plan at Crystal Palace Park.

 

2.  The procurement of the multi-disciplinary consultancy services to replace AECOM be approved noting that the Regeneration Plan is already on the Capital Programme, with funding secured for the works required under the shadow s106 agreement.

 


Meeting: 08/02/2023 - Executive (Item 155)

PROCUREMENT OF CONSULTANCY SERVICES FOR THE CRYSTAL PALACE PARK REGENERATION PLAN PART 2 APPENDICES

Additional documents:

Minutes:

The Executive noted the Part 2 appendices.