KELSEY PARK LAKE

Meeting: 05/07/2023 - Executive (Item 28)

28 WATERBODY MANAGEMENT: KELSEY PARK LAKE pdf icon PDF 488 KB

Decision:

1.  A variation to idverde’s contract b agreed at a one-off value of £63k to undertake the survey work identified at paragraph 3.10 of the report and prepare the technical specifications for the tender of a works contractor.

2.  It be agreed to proceed to procurement for a works contractor to deliver the project in accordance with the procurement strategy set out in paragraphs 3.21 – 3.24 of the report.

3.  Authority be delegated to the Director of Environment & Public Protection, in consultation with the Portfolio Holder for Sustainability, Green Services and Open Spaces, to award the works contract to the successful tenderer up to the value remaining in the capital programme for the Kelsey Lakes.

4.  A 15-month fixed term Project Manager post be created to deliver the project using the capital programme funding for Kelsey Lakes at an estimated cost of £80k as set out in paragraph 3.27 of the report.

5.   A one-off variation to idverde’s contract of £17.5k for 2023/24 be approved to fund the desilting project at Croydon Canal identified at paragraph 3.29 of the report.

 

Minutes:

Report ES20281

The report recommended that the Council remove silt from Kelsey Lakes to ensure that it meets its responsibilities as a riparian owner and to protect biodiversity.  The report set out the recommended procurement strategy for delivering these works and sought to draw down funding allocated in the capital programme to undertake surveys, prepare the tender for the works and to create a Project Manager post to manage the delivery of this project.  The report also identified desilting projects being undertaken at Croydon Canal and Glassmill Pond.

The report had been scrutinised by the Environment and Community Services PDS Committee at its meeting on 29 June 2023 and the Committee had supported the recommendations.

RESOLVED: That

1.  A variation to idverde’s contract b agreed at a one-off value of £63k to undertake the survey work identified at paragraph 3.10 of the report and prepare the technical specifications for the tender of a works contractor.

2.  It be agreed to proceed to procurement for a works contractor to deliver the project in accordance with the procurement strategy set out in paragraphs 3.21 – 3.24 of the report.

3.  Authority be delegated to the Director of Environment & Public Protection, in consultation with the Portfolio Holder for Sustainability, Green Services and Open Spaces, to award the works contract to the successful tenderer up to the value remaining in the capital programme for the Kelsey Lakes.

4.  A 15-month fixed term Project Manager post be created to deliver the project using the capital programme funding for Kelsey Lakes at an estimated cost of £80k as set out in paragraph 3.27 of the report.

5.   A one-off variation to idverde’s contract of £17.5k for 2023/24 be approved to fund the desilting project at Croydon Canal identified at paragraph 3.29 of the report.