Decision:

That

 

1)  The relocation of the Mottingham Community Support Centre to be co-located with Castlecombe Youth Centre be agreed.

 

2)  It be noted that up to £1.153m of the OPR budget as planned will be used for the repair and remodelling works for Castlecombe Youth Centre to make the site fit for purpose for both services.

 

3)  It be agreed to proceed to procurement for the works contract at an estimated value of £1.038m as set out in paragraphs 3.17 to 3.20 of the report, with delegated authority to the Director of Housing, Planning, Property and Regeneration to determine the detailed procurement strategy.

 

4)  Authority be delegated to the Director of Corporate Services and Governance to enter into and manage legal matters relating to these works to allow works to progress.

 

 

Minutes:

Report HPR2023/064

 

As part of the Operational Property Review programme Castlecombe Youth Centre was scheduled for repair. The report requested approval to progress the repair scheme through proceeding to procurement.

 

Additionally, Castlecombe Youth Centre building had been identified as a suitable location for the Mottingham Community Support Centre and therefore the refurbishment of the site needed to be undertaken so that it met this wider service need.

 

The report had been scrutinised by the Renewal, Recreation and Housing PDS Committee at its meeting on 15 November 2023 and the Children, Education and Families PDS Committee at its meeting on 22 November 2023.  Both committees had supported the recommendations.

RESOLVED: That

 

1)  The relocation of the Mottingham Community Support Centre to be co-located with Castlecombe Youth Centre be agreed.

 

2)  It be noted that up to £1.153m of the OPR budget as planned will be used for the repair and remodelling works for Castlecombe Youth Centre to make the site fit for purpose for both services.

 

3)  It be agreed to proceed to procurement for the works contract at an estimated value of £1.038m as set out in paragraphs 3.17 to 3.20 of the report, with delegated authority to the Director of Housing, Planning, Property and Regeneration to determine the detailed procurement strategy.

 

4)  Authority be delegated to the Director of Corporate Services and Governance to enter into and manage legal matters relating to these works to allow works to progress.