(11/01176/FULL1) - Bromley Service Station, 116 Hastings Road, Bromley.

Decision:

PERMISSION

Minutes:

Description of application - Installation of 2 underground fuel tanks, 4 petrol pump islands, resurfacing of forecourt and new forecourt canopy.

 

  Oral representations in objection to the application were received at the 

meeting.  It was noted that on page 29 of the Chief Planner’s report the first  sentence of the fourth paragraph should be deleted.

  Members having considered the report, objections and representations, RESOLVED THAT PERMISSION BE GRANTED as recommended, for the reasons and subject to the conditions and informatives set out in the report of the Chief Planner with the deletion of condition 9 and the addition of two further conditions to read:-

“14.  Details of the proposed slab levels of the building(s) and the existing site levels shall be submitted to and approved in writing by the Local Planning Authority before work commences and the development shall be completed strictly in accordance with the approved levels.

REASON: In order to comply with Policy BE1 of the Unitary Development Plan and in the interest of the visual and residential amenities of the area.

 15.  Whilst the development hereby permitted is being carried out, construction shall not take place before 08:30 hours nor after 18:00 hours Mondays to Fridays, before 09:00 hours nor after 16:00 hours on Saturdays, nor on any Sunday or Bank Holiday.

REASON:  In order to comply with Policies BE1 of the Unitary Development Plan, Policies 4A.19 and 4A.20 of The London Plan, PPS24, and in the interest of the residential amenities of the area.

 

Action By:Chief Planner

Supporting documents: