Agenda item

(14/02507/RESPA) - Temple Gate House, 115-123 High Street, Orpington.

Decision:

PRIOR APPROVAL GRANTED SUBJECT TO CONDITIONS

Minutes:

Description of application - Change of use of office building from Class B1(a) office to Class C3 dwelling house. To provide for 8 one bedroom flats and 13 two bedroom flats (56 day application for prior approval in respect of transport and highways, contamination and flooding risks under Class J Part 3 of the GPDO).

 

It was reported that the Chief Planner’s recommendation on page 115 of the report be amended to read, ‘GRANT PRIOR APPROVAL’.

Members having considered the report, RESOLVED that PRIOR APPROVAL be GRANTED as recommended,subject to the following condition:-

“1.  Before commencement of the use of the land or building hereby permitted parking spaces and/or garages and turning space shall be completed in accordance with the approved details and thereafter shall be kept available for such use and no permitted development whether permitted by the Town and Country Planning (General Permitted Development Order 1995 (or any Order amending, revoking and re-enacting this Order) or not shall be carried out on the land or garages indicated or in such a position as to preclude vehicular access to  the said land or garages.

REASON: In order to comply with Policy T3 of the Unitary Development Plan and to avoid development without adequate parking or garage provision, which is likely to lead to parking inconvenient to other road users and would be detrimental to amenities and prejudicial to road safety.

2.  Details of arrangements for storage of refuse and recyclable materials (including means of enclosure for the area concerned where necessary) shall be submitted to and approved in writing by the Local Planning Authority before any part of the development hereby permitted is commenced and the approved arrangements shall be completed before any part of the development hereby permitted is first occupied, and permanently retained thereafter.

REASON: In order to comply with Policy BE1 of the Unitary Development Plan and in order to provide adequate refuse storage facilities in a location which is acceptable from the residential and visual amenity aspects.

3.  Before any part of the development hereby permitted is first occupied, bicycle parking (including covered storage facilities where appropriate) shall be provided at the site in accordance with details to be submitted to and approved in writing by the Local Planning Authority, and the bicycle parking/storage facilities shall be permanently retained thereafter.

REASON: In order to comply with Policy T7 and Appendix II.7 of the Unitary Development Plan and in order to provide adequate bicycle parking facilities at the site in the interest of reducing reliance on private car transport.

4.  Details of a scheme to light the access drive and car parking areas hereby permitted shall be submitted to and approved in writing by the Local Planning Authority before the development hereby permitted is commenced. The approved scheme shall be self-certified to accord with BS 5489 - 1:2003 and be implemented before the development is first occupied and the lighting shall be permanently retained thereafter.

REASON: In order to comply with Policy T3 and Appendix II of the Unitary Development Plan in the interest of visual amenity and the safety of occupiers of and visitors to the development.

5.  Prior to the commencement of the development hereby permitted a Construction Management Plan shall be submitted to and approved in writing by the Local Planning Authority.  The Plan shall include measures of how construction traffic can access the site safely and how potential traffic conflicts can be minimised; the route construction traffic shall follow for arriving at and leaving the site and the hours of operation, but shall not be limited to these. The Construction Management Plan shall be implemented in accordance with the agreed timescale and details.

REASON: In order to comply with Policy T5, T6, T7, T15, T16 & T18 of the Unitary Development Plan and in the interest of the amenities of the adjacent properties.

6.  Surface water from private land shall not discharge on to the highway. Details of the drainage system for surface water drainage to prevent the discharge of surface water from private land on to the highway shall be submitted to and approved in writing by the Local Planning Authority prior to commencement of works. Before any part of the development hereby permitted is first occupied, the drainage system shall be completed in accordance with the approved details and shall be retained permanently thereafter.

REASON: To ensure a satisfactory means of surface water drainage and to accord with Policy ER13 of the Unitary Development Plan.

7.  Before the development hereby permitted is occupied arrangements shall be agreed in writing with the Local Planning Authority and be put in place to ensure that, with the exception of disabled persons, no resident of the development shall obtain a resident's parking permit within any controlled parking zone which may be in force in the vicinity of the site at any time.

REASON: In order to comply with Policy T3 of the Unitary Development Plan and to avoid development without adequate parking or garage provision, which is likely to lead to parking inconvenient to other road users and would be detrimental to amenities and prejudicial to road safety.”

 

Supporting documents: