Issue - decisions

Congestion Relief Scheme – Heathfield Road / Westerham Road

03/12/2014 - Congestion Relief Scheme – Heathfield Road / Westerham Road; Proposed Roundabout

(1)  The proposed congestion relief scheme previously set out in Report ES13094 and shown on drawing ESD/11473-01 is approved.

 

(2)  The decision on final scheme design is delegated to the Executive Director of Environment and Community Services, following consultation with Ward Councillors and the Environment Portfolio Holder.

 

(3)  Implementation of the scheme be delayed until the Cherry Lodge development is completed.

 

(4)  Officers consider measures to help reduce speeds through Keston Village and improve road safety.

 

(5)  TfL continue to be lobbied on measures to improve the Keston Mark junction.