Issue - decisions

POST COMPLETION REVIEW REPORT - REPLACEMENT CHILLERS AT CENTRAL LIBRARY/CHURCHILL THEATRE

03/11/2017 - POST COMPLETION REVIEW REPORT - REPLACEMENT CHILLERS AT CENTRAL LIBRARY/CHURCHILL THEATRE

1)  The findings of the Post Completion Reviews carried out in respect of Replacement Chillers at Central Library/Churchill Theatre be endorsed.

 

2)  The removal of the unspent balance of £36k from the capital programme be noted.