That
1. Proceeding to procurement, as set out in paragraphs 3.12 to 3.26, for a main contractor to deliver the capital works at a total estimated contract cost of £17.7m be approved.
2. The budget of the Crystal Palace Park Regeneration Plan already on the Capital Programme by £19.096m be increased. The scheme will be funded through a £5m grant from the National Lottery Heritage Fund and the capital receipts from the sale of the two areas of parkland which are estimated to achieve £19.36m.